Road Work in the City

All Road Work Maps:
Overall City Road Work Map
Road Work Maps By Quadrant:

NW NE
SW SE

About This Map

Currently showing:

All items in effect between Thursday, September, 2 and Thursday, September, 9

Change dates and items shown
77 Avenue (Patterson to 99 St.): 
Capital Project - Overlay  
(Aug 26-Oct 15) 85 Avenue - Cul-de-sac to Poplar Drive (South side) : 
Capital Project - Sidewalk Program 
(Aug 1-Oct 29) 84th Ave - Wapiti Rd. to 116 St.: 
84th Ave Arterial Road Widening 
(Aug 23-Oct 30) 69 Avenue (94 St. to 98 St.): 
Capital Project - Road Rehabilitation 
(Aug 23-Oct 15) 100 Ave and 99 St: 
Sidewalk replacement 
(Aug 31-Sep 8) 98 Street - Upgrade (101 - 104 Ave): 
Capital Project  
(Aug 1-Oct 29) 84 Avenue - Twinning (108 - 116 St.) & Signals/Trails & Paths: 
Capital Project  
(Jun 14-Oct 29) 63 Avenue (94 St. to 96 St.) : 
Capital Project - Overlay  
(Aug 26-Oct 15) 87 Avenue - 96 St to 95 St. (Both sides) : 
Capital Project - Sidewalk Program 
(Aug 1-Oct 29) 85 Avenue - 96 St. to 95 St. (North Side) - Sidewalk: 
Capital Project - Sidewalk Program 
(Aug 1-Oct 29) 96 - 95 St. to end of cul-de-sac (Both sides) : 
Capital Project - Sidewalk Program 
(Aug 1-Oct 29) 95 Street - 87 Ave - 85 Ave (Both sides): 
Capital Project - Sidewalk Program 
(Aug 1-Oct 29) Mission Height Drive (84 Ave. to 76 Ave): 
Capital Project - Road Rehabilitation 
(Sep 1-Sep 15) Bear Creek Slope 68 St. - 84 Ave. Behind Safeway: 
Capital Project  
(Sep 6-Sep 30) 100 Avenue - 108 - 106  Street: 
2009 Road Rehabilitation  
(Jul 28-Sep 3) 68 Ave Upgrade  - Resources Road to Poplar Drive: 
Capital Project  
(Jul 5-Sep 24) Resources Road from 87 Ave - 95 Ave - Overlay Program: 
Thermoplastic Paint Lines - Overlay Program 
(Jul 31-Oct 29) 116 Avenue (Tracks to Lakeland Drive): 
Capital Project - Road Rehabilitation 
(Sep 6-Sep 30) 102 Street West Side (117 - 120 Avenue) : 
Capital - Trails & Paths 
(Sep 7-Oct 29) 10012 100 Ave: 
Turcon Construction 
(Aug 24-Sep 30) 88 St. from 100 - 116 Ave. : 
Excavation 
(Jun 14-Sep 30) 88 Street - 103 - 112 Avenue: 
Road Closed 
(Jun 11-Dec 1) Blank City Map

Items listed in order of starting date

Road Construction

77 Avenue (Patterson to 99 St.)

Thursday, August 26 to Friday, October 15
Capital Project - Overlay
Primarily overlay of existing structure, minor concrete repairs, manhole & catch basin repairs, milling. Consultant - Genivar, contractor - Reco Construction
Road Construction

85 Avenue - Cul-de-sac to Poplar Drive (South side)

Sunday, August 1 to Friday, October 29
Capital Project - Sidewalk Program
Renovate & replacement of significant portions of concrete sidewalk. Catchbasin & Manhole repairs/replacements. Minor upgrades to underground storm system. Consultant - Focus Contractor - Rulam Contracting Ltd.
Road Construction

84th Ave - Wapiti Rd. to 116 St.

Monday, August 23 to Saturday, October 30
84th Ave Arterial Road Widening
Consultant - Genivar Contractor - Wapiti Capital Project
Road Construction

69 Avenue (94 St. to 98 St.)

Monday, August 23 to Friday, October 15
Capital Project - Road Rehabilitation
Major road reconstruction, concrete repairs, manhole & Storm System repairs paving. Consultant - Genivar Contractor Wapiti Gravel Traffic control - speed reduction from July 15th - Sept. 30th. Barricaded - Patience will be required.
Road Construction

100 Ave and 99 St

Tuesday, August 31 to Wednesday, September 8
Sidewalk replacement
The Yardmaster Ltd. - Sidewalk replacement in front of the Scotia Bank, parking lane closed only
Road Construction

98 Street - Upgrade (101 - 104 Ave)

Sunday, August 1 to Friday, October 29
Capital Project
98 Street Upgrade from 101 Ave. to 104 Ave. Future Couplet Intersection. Rehabilitation will occur along a portion of 103 Ave. adjacent to Library/Art Gallery. Consultant - Focus - Contractor to be decided. See map on web site.
Road Construction

84 Avenue - Twinning (108 - 116 St.) & Signals/Trails & Paths

Monday, June 14 to Friday, October 29
Capital Project
Widening of 84 Ave from an urban 2 lane to urban 4 lane cross section btw 108 St - 116 St. Two new eastbound lanes, intersectional treatments and storm sewer. Traffic signals @ 84 Ave & 113 St. Topsoil & landscapting, Asphalt trail installation. Consul
Road Construction

63 Avenue (94 St. to 96 St.)

Thursday, August 26 to Friday, October 15
Capital Project - Overlay
Primarily overlay of existing structure. Minor concrete repairs, manhole, catch basin repairs, & milling. Consultant - Genivar, Contractor - Reco Construction
Road Construction

87 Avenue - 96 St to 95 St. (Both sides)

Sunday, August 1 to Friday, October 29
Capital Project - Sidewalk Program
Renovate & replacement of significant portions of concrete sidewalk. Catchbasin & Manhole repairs/replacements. Minor upgrades to underground storm system. Consultant - Focus Contractor - Rulam Contracting Ltd.
Road Construction

85 Avenue - 96 St. to 95 St. (North Side) - Sidewalk

Sunday, August 1 to Friday, October 29
Capital Project - Sidewalk Program
Renovate & replacement of significant portions of concrete sidewalk. Catchbasin & Manhole repairs/replacements. Minor upgrades to underground storm system. Consultant - Focus Contractor - Rulam Contracting Ltd.
Road Construction

96 - 95 St. to end of cul-de-sac (Both sides)

Sunday, August 1 to Friday, October 29
Capital Project - Sidewalk Program
Renovate & replacement of significant portions of concrete sidewalk. Catchbasin & Manhole repairs/replacements. Minor upgrades to underground storm system. Consultant - Focus Contractor - Relam Contracting Ltd.
Road Construction

95 Street - 87 Ave - 85 Ave (Both sides)

Sunday, August 1 to Friday, October 29
Capital Project - Sidewalk Program
Renovate & replacement of significant portions of concrete sidewalk. Catchbasin & Manhole repairs/replacements. Minor upgrades to underground storm system. Consultant - Focus Contractor - Rulam Contracting Ltd.
Lane Closure

Mission Height Drive (84 Ave. to 76 Ave)

Wednesday, September 1 to Wednesday, September 15
Capital Project - Road Rehabilitation
Major road reconstruction, concrete repairs, manhole & Storm system repairs paving. Consultant - Genivar Contractor - Wapiti Gravel Flag person should be present all the time to re-route traffic.
Road Construction

Bear Creek Slope 68 St. - 84 Ave. Behind Safeway

Monday, September 6 to Thursday, September 30
Capital Project
Undertake detailed engineering studies on the condition & stability of the Bear Creek Corridor & implement remedial measures as recommended. Restoration of existing outfalls. Consultant - Parkland Geotechnical Ltd. Contractor to be determined.
Road Construction

100 Avenue - 108 - 106 Street

Wednesday, July 28 to Friday, September 3
2009 Road Rehabilitation
Signal lane closure on 2 lane one way traffic, traffic will be maintained during construction. Excavation of clay, to supply and place GBS & Colored Stamped Concrete. Consultant - Genivar Contractor - Wapiti
Road Construction

68 Ave Upgrade - Resources Road to Poplar Drive

Monday, July 5 to Friday, September 24
Capital Project
Upgrade from 2 lane rural to 4 lane urban roadway. Upgrade Traffic Signals @ Poplar Drive. Upgrade intersection @ Resources for 4 lane E-W. Consultant - BLK. Contractor - Knelsen Rock Products.
Lane Closure

Resources Road from 87 Ave - 95 Ave - Overlay Program

Saturday, July 31 to Friday, October 29
Thermoplastic Paint Lines - Overlay Program
Contractor - AAA Stripping & Seal Coating Services
Road Construction

116 Avenue (Tracks to Lakeland Drive)

Monday, September 6 to Thursday, September 30
Capital Project - Road Rehabilitation
Major road reconstruction, concrete repairs, manhole & storm system repairs paving. Consultant - Genivar Contractor - Wapiti Gravel
Road Construction

102 Street West Side (117 - 120 Avenue)

Tuesday, September 7 to Friday, October 29
Capital - Trails & Paths
Trails & Paths
Road Construction

10012 100 Ave

Tuesday, August 24 to Thursday, September 30
Turcon Construction
Fence installation in front of Midwest Furtiture
Road Construction

88 St. from 100 - 116 Ave.

Monday, June 14 to Thursday, September 30
Excavation
Main powerline underground feeders, along Copperwood road, crossing to PUL and north 300 m.
Road Closure

88 Street - 103 - 112 Avenue

Thursday, June 11 to Tuesday, December 1
Road Closed
Road will be closed indefinite. This road is not part of the road network.

About This Map

Information is updated daily.
If known, some changes may be made during the day.

Items shown on this map:

  • Road Construction IconRoad Construction: ongoing roadwork may affect traffic. Reduced speed zones may be in place.
  • Excavation IconExcavation: short-term work adjacent to roadway. Traffic may be briefly interrupted.
  • Lane Closure IconLane Closure: road capacity is reduced. Traffic can still pass through.
  • Detour IconDetour: road is closed to through traffic. An alternate route must be taken.
  • Road Closure IconRoad Closure: road is not accessible. No alternate routes are available.

Items not shown on this map:

  • Traffic interruptions due to accidents and emergencies
  • Frequently moving work such as snow removal and line painting
  • Roadwork being done in areas of new development

Do you:

  • Need to partially block or temporarily close a roadway or sidewalk?
    You probably need a free permit. Contact us to find out more.

  • See work that is not indicated on this map?
    Let us know.

  • Have questions about the work being done?
    Contact us. We can let you know about City-related road projects. 

Our Contact information:

Engineering Services (Transportation and Roads)
engineering_contacts@cityofgp.com
(780) 538-0417