Capital Projects:

2017/2018 Road Rehabilitation and Overlay:

About the Project:

Road Rehabilitation is one of Engineering Services' annual projects. The City uses the Road Rehabilitation and Overlay programs to increase the life cycle of current roads. Road priorities are set based on the results of the assessment process.

Budget:

The approved budget for this project is $8,000,000.00. Funding supplied by: Municipal Sustainability Initiative Grant, Capital Tax and Gas Tax.

Timeline:

The construction schedule is from June to October, 2018.

Rehabilitation and Overlay General Scope: 

  • Major road reconstruction 
  • Major and minor manhole and storm system repairs
  • Paving
  • Concrete repairs and replacement Patterson P-Loop 2018

2018 Road Rehabilitation Locations:
Phase 1:

  • 97 Ave. between 112 St. and 116 St.
  • 112 St. between 97 Ave. and 100 Ave. (Hwy 43)
  • Mission Height Drive between Kateri Dr. and 76 Ave.
  • Patterson P Loop off 76 Ave. (94 St. / 94A St. / 78 Ave. / 77 Ave.) 

Phase 2:

  • 84 St. between 68 Ave. and 100 Ave.
  • 116 Ave. between east of 98 St. (railway crossing) and 100 St.
  • 98/99 St. between 112 St. and 121 Ave.

Phase 3: Patterson Overlay 2011

  • 101 Ave. between 120 St. and 123 St.
  • 104 Ave. and 106 Ave. between 121 St. and 123 St.
  • 121 St. and 123 St. between 101 Ave. and 106 Ave. 
  • Landing Dr. between 100 Ave. and 104 Ave.
  • 90 St. between 95 Ave. and 100 Ave.
  • 96 Ave. between 90 St. and 92 St.

Phase 4:

  • 100 Avenue from 105 Street to 108 Street

Contact Information:

The engineering contract was awarded to Beairsto and Associates Engineering Ltd. at #101, 10940 92 Ave., Grande Prairie, AB. T8V 6B5.

The construction contracts:

  • Phase 1: Wapiti Gravel Suppliers, 4201 93 Street, Grande Prairie, AB. T8V 6T4
  • Phase 2: Wapiti Gravel Suppliers, 4201 93 Street, Grande Prairie, AB. T8V 6T4
  • Phase 3: Knelsen Sand & Gravel Ltd., 9801-156 Ave, Box 21119, Grande Prairie, AB. T8V 6W7
  • Phase 4: Contract has yet to be awarded. 

The City of Grande Prairie's Engineering Services project contact: Daniel Dawson, 780-538-0306, ddawson@cityofgp.com.

102 Street Geometric Upgrades

About the Project: 102 Street Upgrades

The basis for this project comes from the 102 St. Traffic Study, which was adopted in 2014. This study revealed the congestion at the intersection of 102 St. and 117 Ave. While many solutions were discussed, it has been decided that the best option to allow the road to handle the current and future traffic volumes is to implement concrete medians to aid in traffic flow. These medians will be placed to allow the intersection to follow a right-in right-out model once construction is completed. This solution allows for higher current traffic volumes and addresses any current safety concerns.

Budget:
Approved in 2017, the budget for the 102 St. Geometric Upgrades is $670,000. Funding supplied by: Municipal Sustainability Initiative Grant and Capital Tax.

Timeline:

The construction schedule is from May - July, 2018.

Contact Information:

The engineering contract was awarded to Beairsto and Associates Engineering Ltd. at 101 10940-92 Ave., Grande Prairie, AB. T8V 6B5.

The construction contract was awarded to Reco Construction, Lot 17 17 Hwy 40 Industrial Park, Grande Prairie, AB. T8V 3A5.

The City of Grande Prairie's Engineering Services project contact: Mark Hoseasson, 780-830-7447, mhoseasson@cityofgp.com.

Downtown Rehabilitation and Streetscape Upgrades:

About the Project: Farmer's Market 10.19.2017

The Downtown Rehabilitation and Streetscape Upgrades are to address aging infrastructure within the downtown core, both below and above ground, and to create a more attractive downtown in the process. The work is divided into four separate phases:  

Phase 1: 101 Street from 98 Avenue to north of 102 Street (substantially completed in 2017)

Phase 2: 101 Avenue between 1the Golden Age Centre to 100 Street (substantially completed in 2017)

Phase 3: 100 Avenue between 102 Street to 100 Street

Phase 4: 100 Avenue between 100 Street to 98 Street

For more information about this project, please visit: www.cityofgp.com/ourdowntown

Budget:
101 Ave. 10.27.2017
The City has received $15,000,000.00 in General Debenture and Aquatera Utilities has contributed $2,600,000.00 for sewer and water upgrades.

General Scope of Work:

  • Deep utilities (sanitary, storm and water)
  • Urban roadways (shallow utilities, sidewalks and walkways, curb and gutter and roads)
  • Streetscape elements (planting, furniture, street lights and other special features)

Timeline: 

  • Phase 1: Design - 2015/16, Construction - Completed in 2017
  • Phase 2: Design - 2015/16, Construction - Completed in 2017
  • Phase 3: Design - 2017, Construction - 2018
  • Phase 4: Design - 2017/18, Construction - Planned for 2019 (subject to budget) 

Contact Information:

The engineering contract was awarded to ISL Engineering and Land Services Ltd. Suite 100, 7909-51 Ave. NW Edmonton, AB. T6E 5L9.

The construction contract for Phase 3 was awarded to Wapiti Gravel Suppliers, 4201 93 Street, Grande Prairie, AB T8V 6T4.

The City of Grande Prairie's Engineering Services project contact: Conor Coney, 780-538-0361, cconey@cityofgp.com.

116 Street Asphalt Overlay and Culvert Bridge Replacement:

About the Project:

The primary objective of this project is to extend the service life of the road by laying a new asphalt overlay and replacing an old bridge-sized culvert with a new, larger bridge culvert. These upgrades are intended to handle current and future traffic and water volumes. The construction takes place along 116 Street between 68 Avenue and the south city limit.

Budget:

The approved 2017 budget for the 116 Street Asphalt Overlay and Culvert Bridge Replacement is $955,000.00.

Timeline:

This project is anticipated to be completed during the 2018 construction season.

Contact Information:

The engineering contract was awarded to Allnorth, 10530 117 Ave., Grande Prairie, AB. T8V 7N7.

The construction contract was awarded to Reco Construction, Lot 17 17 Hwy 40 Industrial Park, Grande Prairie, AB. T8V 3A5.

The City of Grande Prairie's Engineering Services project contact: Daniel Dawson, 780-538-0306, ddawson@cityofgp.com.

68 Avenue Twinning:

About the Project:

This project is for the design of a four lane divided arterial roadway from 108 St to Poplar Dr. The work also includes a new traffic bridge over Bear Creek. For more detailed information please see our 68 Ave. project specific page.

68 Avenue Concept Drawings (PDF, 5992KB)

Budget:

The approved 2016 budget for the 68 Avenue Twinning project is $10,750,000.00 and it comes from Transportation System Levy Reserve, the Municipal Sustainability Initiative Grant and General Debenture. Funding is broken down as follows:

68 Avenue Twinning and Bridge Design 68 Ave Bridge

  • 2015: $750,000.00

Bridge Construction

  • 2015/16: $4,000,000.00

Road Twinning/Construction

  • 2016: $6,000,000.00

Timeline:

The construction schedule is from May - October, 2016.

Contact Information:

The engineering contract was awarded to Beairsto and Associates Engineering Ltd. at 101 10940-92 Ave., Grande Prairie, AB. T8V 6B5.

The road construction contract was awarded to Knelsen Sand & Gravel Ltd., 9801-156 Ave, Box 21119, Grande Prairie, AB., T8V 6W7 and the bridge construction contract was awarded to Eiffage Innovative Canada Inc.

The City of Grande Prairie's Engineering Services project contact: Daniel Dawson, 780-538-0306, ddawson@cityofgp.com.