Road Rehabilitation on Lakeland Drive

Current  Closure

Currently, there are no closures on Lakeland Drive. Previous closures are shown in the map below.

Lakeland Drive 1

Background

This project is part of the 2017 Road Rehabilitation and Overlay Program. Road Rehab is one of Engineering Services annual projects. The City uses the Road Rehabilitation and Overlay Programs to increase the life cycle of current roads. Road priorities are set based on the results of the assessment process.

Construction work began with a milling procedure along this stretch of road. The milling process entails grinding the top layer of pavement off of the road. The road remained open during initial milling activities.

Crews then begin working on various road components in sections. Initial work included catch basin repairs, culvert replacements and storm work. During this time, alternating sections of the road shut down to accommodate work. These sections are depicted in the photo above.

Work has now began on removing the remaining portions of the road. This removal will be followed immediately with the laying and filling of gravel to create a new base for the road. This work is also to be competed in three sections.

Following the completion of the road removal, concrete work and paving activities begin.

Traffic Information

Traffic in the area is reminded to proceed through the construction zone with caution and to watch for workers at all times. Detours will be announced and updated as the project moves forward. Keep checking our website, social media and weekly updates for the latest information.