Downtown Rehabilitation Project Road Openings and Construction Update
Posted Date: 11/2/2017

Construction on the Downtown Rehabilitation Project is scheduled to be completed by mid-November, 2017.


Road Openings and Pedestrian Access

101 Street and 101 Avenue between 101 Street and 100 Street are anticipated to be open to vehicle traffic late next week. 101 Avenue between 102 Street and 101 Street is anticipated to be open to vehicle traffic by mid-November. This is depicted in the map below.

DT Rehab


Pedestrians are permitted to use all sidewalks to access businesses in the Downtown. Crews continue to work in isolated and marked areas. Pedestrians are asked to use caution and avoid areas where crews are working.


Remaining Work

In late October, crews completed the majority of paving stone installation. The remaining paving stone installation surrounds concrete seat walls and will be completed upon their final placement.

DT Rehab  DT Rehab

[Paving stones at the intersection of 101 Avenue and 101 Street. An example of the concrete seat walls on 101 Avenue.]



Remaining work on the project includes the installation of concrete seat walls, construction site clean-up, and the installation of street furniture.

For up-to-date information or to sign-up for the Weekly Update e-newsletter visit cityofgp.com/ourdowntown.