Manufactured Home

Permits

A lot grading, development, building and all subtrade (electrical, plumbing and gas) permits are required to set a Manufactured Home.

Step 1: Apply

Complete a Residential Permit Application. This package allows you to submit one application when applying for all the required permits. There is no requirement to apply for all at one time, however to minimize wait time, we do suggest applying for all permits at once.

Step 2: Approval

Once a complete application is received, all permits will be issued within 2- 5 business days.

If a variance is required, timelines may extend up to 25 days.

Step 3: Construction

You may begin construction once you have received all required permits. Below is contact information you may need for ground work and utilities.

Step 4: Inspections

Please see below for how to make your inspection requests.

All required inspections are listed on the conditions issued with the permit.

You may request an inspection online.